秦南文化活动中心办公楼工程量清单计价文件的(附件)【字数:18758】

摘 要
本次毕设题目为对秦南文化活动中心办公楼工程量清单计价文件的编制,该工程位于江苏省盐城市,地上6层,总建筑面积为4633.8㎡,框架结构,结构类别为三类。通过研读该工程的建筑施工图和结构施工图的设计说明可以了解该工程各部分的做法及要求,并阅读《房屋建筑与装饰工程工程量计算规范》(GB 508542013),按照其目录顺序对各部分进行工程量计算,具体包括土石方工程、桩基工程、混凝土及钢筋混凝土工程、门窗工程、屋面及防水工程、保温隔热工程、楼地面装饰工程等,同时还需要结合《建设工程工程量清单计价规范》(GB 505002013)、江苏省定额以及近期的市场价格为指导,算出该项目分部分项工程的综合单价。最终计算汇总得出秦南文化活动中心办公楼的工程总造价。
ABSTRACT
The project was completed on the preparation of the bill of quantities for the construction of the Qinnan Cultural Activity Center office building. The project is located in Yancheng, Jiangsu Province, with 6 floors above ground and a total construction area of 4633.8m2. The frame structure and structure category are three types. Through reading the design drawings of the construction drawings and structural drawings of the project, you can learn about the practices and requirements of each part of the project, and read the “Code for the Calculation of the Amount of House Construction and Decoration Engineering” (GB 508542013), in a *好棒文|www.hbsrm.com +Q: ^351916072* 
ccordance with the directory order. The project volume calculation is performed for each part, including earth and stone works, pile foundation engineering, concrete and reinforced concrete works, door and window projects, roofing and waterproofing projects, thermal insulation projects, floor decoration projects, etc., as well as the need to combine "construction engineering projects. "Specifications for Valuation of List Price" (GB 505002013), Jiangsu quotas, and recent market prices are the guideline for the calculation of the overall unit price for the subprojects of this project. The final calculation sums up the total project cost of the office building of Qinnan Cultural Activity Center.
Key words:Calculation rules;Engineering quantity; inventory pricing; quota; integrated unit pric 目 录
第一章 设计简介 1
1.1设计依据 1
1.2项目基本概况 1
第二章 工程量计算 3
2.1概述 3
2.2建筑分部分项工程量计算 4
2.3措施项目工程量计算 17
第三章 定额套用 19
3.1清单项目综合单价 19
3.2定额套用 19
3.3定额换算 19
第四章 工程取费 22
4.1工程类别 22
4.2措施项目费 22
4.3其他项目费 24
4.4规费和税金 24
第五章 清单计价文件汇总 24
5.1编制说明 25
5.2单项工程费用汇总表 25
5.3单位工程费用汇总表 25
5.4分部分项工程费用汇总表 26
5.5措施项目费用汇总表 30
5.6其他项目费用汇总表 30
5.7规费、税金项目费用汇总表 31

版权保护: 本文由 hbsrm.com编辑,转载请保留链接: www.hbsrm.com/jzgc/tmgc/219.html