绿地绿化工程施工方案(附件)【字数:12043】
本项目施工设计方案主要是关于某一地块新建绿地主体绿化工程施工的方案。编制时主要考虑了项目的质量和安全问题,同时注重施工中的组织协调计划,将施工中所需的人力、物力以及财力准备到位,保证在预定工期内保质保量地完成任务。
本工程施工管理方案主要内容包括:引言、工程基本概况、施工计划部署及施工管理方法、质量安全保证管理措施等。为有效确保工期、质量、安全等,方案要求各施工班组及合作单位严格按照其中的具体措施实施具体施工,将方案中的要求落到实处。
Abstract
The construction design plan of this project is mainly about the main construction project of the new greening main greening project in a certain land of a certain city. The main consideration in the preparation is the quality and safety of the project. At the same time, it pays attention to the organization and coordination plan during the construction, and prepares the manpower, material and financial resources required in the construction to ensure that the task is completed within the predetermined period of time and quality.
The main contents of the project construction management plan include: introduction, basic project overview, construction plan deployment and construction management methods, quality and safety assurance manag *好棒文|www.hbsrm.com +Q: @351916072@
ement measures, etc. In order to effectively ensure the construction period, quality, safety, etc., the plan requires all construction teams and cooperative units to implement specific construction in strict accordance with the specific measures therein, and implement the requirements in the plan.
Keywords: Construction scheme;Scientific management;Overall planning.
目录
一、引言 1
二、 编制依据 1
三、 工程概况 1
(一)项目概况 1
(二)工程文字说明 2
四、施工准备 2
五、施工部署 4
(一)工艺流程图 4
(二)各项验收工序的质量验收要求 5
(三)各工程分项落叶苗木工程施工的基本技术要求和保障管理措施 6
六、 施工质量保证管理措施 10
(一)质量目标 10
(二)施工质量目标保证管理措施 10
七、环保及安全文明措施 10
(一)文明施工 10
(二) 环境的保护 11
(三)安全管理施工措施 11
八、施工进度安排计划及保证进度安排措施 12
(一)计划制定进度和工期计划的原则 12
(二)工期安排 12
(三)关于确保工期的措施 12
九、 绿化种植后期养护措施 13
(一)乔(灌)木的养护期管理 13
(二)草坪养护管理措施 13
十、成品保护措施 14
十一、结论 14
十二、致谢 14
参考文献 15
一、引言
施工设计方案是为了正确实现基本设计和工程设计师的要求,建立正常合理的安全施工操作程序,有序按计划的组织实施各种安全施工管理过程的文件。为各种工程施工的及时性和准备工作提供重要依据,保证各种劳动力以及各种施工材料的及时供应以及正常使用。协调每个工程施工单位的施工秩序,每个工种之间,每种施工资源之间的相互合理分配关系。对于建筑施工安全过程管理中的施工技术、质量、安全清洁生产、文明清洁施工等各个环节工作中的问题都要规定切实可行的质量保证管理措施。
我作为一名建筑系的大学生有幸在这所高校实习期间详细地了解和接触到这些绿化方面的知识和内容,并且也产生了浓厚的学习兴趣。为此,我与老师共同收集资料,加上这个工程施工项目的绿地规划和绿化的施工图、工程量清单以及其相关的工程技术管理操作规范,综合起来特编制此工程绿地绿化的施工项目设计方案。
编制依据
《土建工程操作规程》YL0203
《园林土方工程操作规程》YL0204
《大树移植技术规程》(DBJ08—53—96)
《园林植物养护技术规程》(DBJ081991)
《园林栽植土质量标准》(DBJ08—231—98)
《建筑机械使用安全技术规范》(JGJ33—86)
《建设工程项目管理规范》(GB/T50326—2001)
本工程施工管理方案主要内容包括:引言、工程基本概况、施工计划部署及施工管理方法、质量安全保证管理措施等。为有效确保工期、质量、安全等,方案要求各施工班组及合作单位严格按照其中的具体措施实施具体施工,将方案中的要求落到实处。
Abstract
The construction design plan of this project is mainly about the main construction project of the new greening main greening project in a certain land of a certain city. The main consideration in the preparation is the quality and safety of the project. At the same time, it pays attention to the organization and coordination plan during the construction, and prepares the manpower, material and financial resources required in the construction to ensure that the task is completed within the predetermined period of time and quality.
The main contents of the project construction management plan include: introduction, basic project overview, construction plan deployment and construction management methods, quality and safety assurance manag *好棒文|www.hbsrm.com +Q: @351916072@
ement measures, etc. In order to effectively ensure the construction period, quality, safety, etc., the plan requires all construction teams and cooperative units to implement specific construction in strict accordance with the specific measures therein, and implement the requirements in the plan.
Keywords: Construction scheme;Scientific management;Overall planning.
目录
一、引言 1
二、 编制依据 1
三、 工程概况 1
(一)项目概况 1
(二)工程文字说明 2
四、施工准备 2
五、施工部署 4
(一)工艺流程图 4
(二)各项验收工序的质量验收要求 5
(三)各工程分项落叶苗木工程施工的基本技术要求和保障管理措施 6
六、 施工质量保证管理措施 10
(一)质量目标 10
(二)施工质量目标保证管理措施 10
七、环保及安全文明措施 10
(一)文明施工 10
(二) 环境的保护 11
(三)安全管理施工措施 11
八、施工进度安排计划及保证进度安排措施 12
(一)计划制定进度和工期计划的原则 12
(二)工期安排 12
(三)关于确保工期的措施 12
九、 绿化种植后期养护措施 13
(一)乔(灌)木的养护期管理 13
(二)草坪养护管理措施 13
十、成品保护措施 14
十一、结论 14
十二、致谢 14
参考文献 15
一、引言
施工设计方案是为了正确实现基本设计和工程设计师的要求,建立正常合理的安全施工操作程序,有序按计划的组织实施各种安全施工管理过程的文件。为各种工程施工的及时性和准备工作提供重要依据,保证各种劳动力以及各种施工材料的及时供应以及正常使用。协调每个工程施工单位的施工秩序,每个工种之间,每种施工资源之间的相互合理分配关系。对于建筑施工安全过程管理中的施工技术、质量、安全清洁生产、文明清洁施工等各个环节工作中的问题都要规定切实可行的质量保证管理措施。
我作为一名建筑系的大学生有幸在这所高校实习期间详细地了解和接触到这些绿化方面的知识和内容,并且也产生了浓厚的学习兴趣。为此,我与老师共同收集资料,加上这个工程施工项目的绿地规划和绿化的施工图、工程量清单以及其相关的工程技术管理操作规范,综合起来特编制此工程绿地绿化的施工项目设计方案。
编制依据
《土建工程操作规程》YL0203
《园林土方工程操作规程》YL0204
《大树移植技术规程》(DBJ08—53—96)
《园林植物养护技术规程》(DBJ081991)
《园林栽植土质量标准》(DBJ08—231—98)
《建筑机械使用安全技术规范》(JGJ33—86)
《建设工程项目管理规范》(GB/T50326—2001)